SOW Report
Contract 84044 REL 40: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Project Number:
Title:
Lolo/Selway River Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
84044 REL 40
Contract Title:
1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
84044 REL 13: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Contract Status:
Issued
Contract Description:
The Lolo Creek Watershed Restoration project (1996-077-02) has been an on-going project of the Nez Perce Tribe Fisheries Watershed Program and BPA since 1996. This unique and successful restoration partnership is implemented through agreements between the Nez Perce - Clearwater National Forests (NPCNFs), Nez Perce Tribe (NPT), and Bonneville Power Administration (BPA). The ultimate goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural, and economic practices of the Nez Perce Tribe. In 2016, the Lolo Creek project was combined with the Selway River project, a newly funded BiOp effort initiated in 2011 to perform high priority watershed restoration actions in the Selway River watershed.

The Lolo Creek watershed contains designated critical habitat for Snake River steelhead and has moderate habitat potential for Spring Chinook salmon. Bull trout have also been detected within the Lolo Watershed and potential spawning and rearing habitat may be present.  Restoration in this watershed focuses on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing effects, fish passage barriers, and noxious weed infestations. Fish passage and habitat connectivity actions are prioritized primarily at road/stream crossings on both private and federal land, and native riparian re-vegetation and continuous riparian protection are also high priority actions.

The Selway River watershed contains designated critical habitat for Snake River steelhead* and bull trout**, and has moderate habitat potential for Spring Chinook salmon. Restoration follows a ridge top to ridge top approach with implementation focused on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing effects, aquatic habitat connectivity, and exotic, invasive plant encroachment. The cost share for this project has been contributed by the Nez Perce - Clearwater National Forests who provides approximately 20% match including cash and in-kind contributions. Project planning and implementation responsibilities are also shared with the Nez Perce - Clearwater National Forests.

Completed contract work in the Lolo Watershed includes culvert prioritization and assessment, installation of an off-site water source, 31 culvert replacements, 11 culvert removals, 2600 ft. of stream bank stabilization, 14 large wood structures, 108.5 miles of road decommissioning, 23 miles of fence installation and maintenance, and over 24,000 native riparian trees and shrubs planted.

Completed contract work in the Selway Watershed includes culvert prioritization and assessment, installation of 10 culvert replacements, and 41 miles road decommissioning surveys.  

The following agencies and entities will collaborate with local partners to identify the highest priority locations and a corresponding suite of restorations actions to address critical limiting factors in the Lolo Creek Watershed: BPA, NPT, Nez Perce-Clearwater National Forests, IDFG, IDL, Potlatch Deltic Corp., BLM, NRCS, TU, and  Clearwater/Idaho county SWCDs. This collaborative, inclusive, evidence-based, and strategic process has been ongoing for several years, leading to the development of an Atlas prioritization framework in 2019. The Lolo Atlas framework contains a prioritized list of areas and specific restoration actions to be implemented over the next 10 years or more. The Atlas framework is a living document and is managed adaptively and modified as projects are implemented and as new data and research evidence becomes available to inform restoration.

Projects have been considered and prioritized through the Lolo Atlas process, and those planned for implementation in this contract period, include: installation of LW and BDAs, addressing fish passage barriers in several creeks; design work at the Selway irrigation diversion; and fencing, riparian planting, and invasive plants treatment.

*Designated Critical Habitat: Critical Habitat for 19 Evolutionary Significant Units of Salmon and Steelhead in Washington, Oregon, Idaho, and California; Final Rule, 65 Fed. Reg. 7764 (February 16, 2000).

**Revised Designation of Critical Habitat for Bull Trout in the Coterminous United States; Final Rule, 75 Fed. Reg. 63898 (October 18, 2020).
Account Type(s):
Expense
Contract Start Date:
02/01/2024
Contract End Date:
01/31/2025
Current Contract Value:
$683,031
Expenditures:
$102,679

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
David Kaplowe Bonneville Power Administration Yes Supervisor djkaplowe@bpa.gov (503) 230-5365
Eric Leitzinger Bonneville Power Administration Yes F&W Approver ejleitzinger@bpa.gov (503) 230-3534
Ed Main Nez Perce Tribe No Technical Contact edwardm@nezperce.org (208) 621-3539
Justin Peterson Nez Perce Tribe Yes Contract Manager justinp@nezperce.org (208) 621-3545
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023
Ryan Ruggiero Bonneville Power Administration Yes COR RCRuggiero@bpa.gov (503) 230-3789
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Emmit Taylor, Jr. Nez Perce Tribe No Administrative Contact emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Complete Environmental Compliance B: 165. Environmental Compliance for Projects 01/31/2025
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish C: 114. Use ATLAS Matrix to Prioritize and Select Projects 01/31/2025
Install instream structures to improve habitat complexity D: 29. Lolo Creek Instream Complexity, "Knock on Wood Phase II" 01/31/2025
Remove Musselshell Creek Headgate E: 184. Remove Irrigation Diversion on Musselshell Creek 11/29/2024
Musselshell Meadow Wetland Restoration F: 181. Musselshell Meadow Wetland Improvement--Headgate and Diversion Ditch Removal 01/31/2025
Replace Lower Musselshell Creek Bridge G: 85. Lower Musselshell Creek Bridge Replacement 09/30/2024
Submit Final Designs H: 175. Elk City Creek Culvert Design 01/31/2025
Complete O'Hara Rock Pit Improvements I: 55. O'Hara Rock Pit Improvement 01/31/2025
Finalize Construction of Culverts 5 and 8 J: 38. O'Hara Road Improvement, culvert replacement #5 and #8 11/30/2024
Construct Bridge and Road Improvement on SF Running Creek K: 85. South Fork Running Creek Barrier Replacement and Road Improvement 01/31/2025
Complete road improvement feasibility plans through 15 or 30% design L: 175. USFS Road 535 and 103 Road Relocation Feasibility Design 01/31/2025
Remove old log culvert in Slate Creek M: 85. Slate Creek #3 Barrier Removal 01/31/2025
Finalize Construction of BDAs N: 29. Construct Beaver Dam Analogs and/or PALS in Jim Brown and Musselshell creeks 01/31/2025
Develop designs with IDFG for Selway irrigation diversion removal O: 175. Selway Irrigation Diversion Design 01/31/2025
Install O'Hara Creek Bridge P: 85. O'Hara Creek Bridge Replacement 09/30/2024
Produce Design Q: 175. Musselshell Road Improvement Design 01/31/2025
Complete Riparian Planting R: 47. Plant Riparian Vegetation 01/31/2025
Maintain Fence S: 186. Maintain Fence 01/31/2025
Complete all invasive species treatment T: 199. Treat Exotic Invasive Species on USFS and Private Lands 01/31/2025
Complete various assessments U: 115. Collect stream, meadow, road data/Project monitoring and inventory via UAV (i.e., drone) to develop and prioritize future projects 01/31/2025
Complete technical reviews and recommendations V: 122. Review and Technical Assistance for Proposed Partner Actions 01/31/2025
Coordinate with regional partners W: 191. Coordinate with Regional Partners 01/31/2025
Effective implementation management and timely contract administration X: 119. Manage Projects and Administrative duties 01/31/2025
Completed Annual Report Y: 132. Annual Report February 2023 - January 2024 06/30/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 3 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 4 instances of WE 175 Produce Design
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
Freshwater Mussels
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Environmental Compliance for Projects
C 114 Use ATLAS Matrix to Prioritize and Select Projects
D 29 Lolo Creek Instream Complexity, "Knock on Wood Phase II" 12/28/2023
E 184 Remove Irrigation Diversion on Musselshell Creek 12/28/2023
F 181 Musselshell Meadow Wetland Improvement--Headgate and Diversion Ditch Removal 12/28/2023
G 85 Lower Musselshell Creek Bridge Replacement 02/28/2024
H 175 Elk City Creek Culvert Design 10/31/2023
I 55 O'Hara Rock Pit Improvement
J 38 O'Hara Road Improvement, culvert replacement #5 and #8
K 85 South Fork Running Creek Barrier Replacement and Road Improvement
L 175 USFS Road 535 and 103 Road Relocation Feasibility Design 10/31/2023
M 85 Slate Creek #3 Barrier Removal
N 29 Construct Beaver Dam Analogs and/or PALS in Jim Brown and Musselshell creeks 10/31/2023
O 175 Selway Irrigation Diversion Design 10/31/2023
P 85 O'Hara Creek Bridge Replacement
Q 175 Musselshell Road Improvement Design 10/31/2023
R 47 Plant Riparian Vegetation 10/31/2023
S 186 Maintain Fence 10/31/2023
T 199 Treat Exotic Invasive Species on USFS and Private Lands 10/31/2023
U 115 Collect stream, meadow, road data/Project monitoring and inventory via UAV (i.e., drone) to develop and prioritize future projects 10/31/2023
V 122 Review and Technical Assistance for Proposed Partner Actions
W 191 Coordinate with Regional Partners
X 119 Manage Projects and Administrative duties
Y 132 Annual Report February 2023 - January 2024